Bank of Tokyo-Mitsubishi UFJ

Cat A & B Fit Out & Mechanical & Electrical Installation

 

Summary

Client: Bank of Tokyo-Mitsubishi UFJ
Location: London
Sector: Office Fit Out
Project: Cat A & B Fit Out & Mechanical & Electrical Installation

 


 

Call us anytime to discuss your project on
01438 847 020

Bank of Tokyo-Mitsubishi UFJ

Project Overview

JCA were the principal contractor for this design and build project. This £3m project was to be delivered in 18 weeks.

The scope of the project was a combined category A & B fit out in a shell and core new build property. This facility was required as a data recovery centre and emergency trading centre for the client.

The project included the installation and fit out of three floors including all fabric, mechanical and electrical services, including critical infrastructure for a number of comms rooms. Throughout the project there was a high level of co-ordination and liaison with the client and landlord to achieve the specification and client requirements. Specific services provided included new partitioning, ceilings, flooring, air conditioning, LV infrastructure, general power and lighting installations to the offices area, together with critical M & E services for the new comms rooms.

The handover date was critical to the client which resulted in a condensed programme. JCA achieved the required dates for occupation, even with challenging planning issues for the roof mounted equipment and generator plant. JCA worked closely with the client and local planners to ensure that a quality and compliant product was delivered within timescale