Talk Talk Technology

Breckland Data Centre Upgrade

Summary

Client: Talk Talk Technology
Location: Buckinghamshire
Sector: Data Centre
Project: Breckland Data Centre Upgrade

Talk Talk Technology

Project Overview

JCA were asked to carry out extensive capital plant replacement and upgrade work on a 20+ year data centre facility. The works were to be carried out in a live environment with no loss or impact to the client’s services.
A complete refurbishment was carried out to two 500kVA static UPS systems and one 600kVA static UPS system, including full battery replacement. A new fourth 400kVA scalable static UPS system was installed.
JCA completed the installation of new 3200A LV switchboards and the re-configuration of three 2.15 MVA standby generators. The power generation, mechanical and electrical infrastructure, were redesigned to accommodate a fourth 2MVA standby generator and the addition of a further fuel tank, with pipework modification to optimise the standby resilience.